Filtraglass
Banner
Falorni Tech Glass Melting Technology

Vetropack Straža completes furnace reconstruction

On November 21, 2024, the final brick was ceremoniously driven into the crown of the flint furnace at Vetropack Straža, in Hum na Sutli, Croatia, marking the symbolic end of the reconstruction phase and an important milestone for the factory.

The ceremony was officiated by the patrons of the furnace: Minister of Environment and Green Transition Marija Vučković, Managing Director Darko Šlogar, Finance Director Marija Špiljak and Production Director Božo Hršak who used a special mallet to drive the final brick into place. The official program continued inside the furnace, where it will soon hold around 500 tonnes of molten glass ready for production.

The Minister of Environmental Protection and Green Transition, Marija Vučković, as one of the patrons of the furnace, “drove in” the final brick

The furnace modernisation project, that started on September 2nd, 2024 and involved over 300 external workers daily, introduced state-of-the-art technology to enhance production capacity and reduce environmental impact. As Vetropack Straža prepares to produce flint glass in December, this investment sets new standards in efficiency and sustainability for the glass packaging industry.

Increased capacity and greater energy efficiency thanks to modern melting tank
One highlight of the modernisation is the use of an NIS glass-blowing machine with servo drive – the first machine of its kind for Vetropack Straža. An optimised layout throughout the plant has improved the overall production flow. These innovations not only safeguard Vetropack’s high quality standards, but also ensure long-term production and energy efficiency.

The modernised facility is designed to reduce energy consumption and emissions, which helps minimise the carbon footprint and supports Vetropack’s sustainability goals. In addition, the new furnace also increases the throughput ratio, enabling the production of more glass per square metre – saving space and costs.

“I am proud and looking forward to the first glass production with the new machine,” said Mario Berc, Technical Manager at Vetropack Straža. “The commissioning is a significant milestone for us.”

Alexander Sorg, CEO of Sorg, the company that designed the furnace, presented the Managing Director of Vetropack Straža with a gift to mark the completion of the reconstruction

Sign up for free to the glassOnline.com daily newsletter

Subscribe now to our daily newsletter for full coverage of everything you need to know about the world glass industry!

We don't send spam! Read our Privacy Policy for more information.

Share this article
Related news