GMIC: Department of Energy grant update

In 2024, GMIC was awarded a three-year, USD 3 million grant from the Department of Energy to research advanced electric melting to decarbonize commercial glass. Each quarter, GMIC will update members on the research and the milestones achieved.

The objective of the project is to demonstrate melting processes which reduce scope-1 greenhouse gas emissions by 85 percent and more for large volume, commercial glass production. The focus will be on overcoming three barriers which have hindered adoption of all-electric glass furnaces:

  • Production of dark/reduced coloured glasses (e.g. amber)
  • Improve quality of clear glass
  • Furnace lifetime

The project launched in the last quarter of 2024, and accomplishments last quarter included:

  • Establishing the project lab and modelling capabilities
  • Setting up the Cold-Top Melting Furnace
  • Testing the pelletizing set up
  • Completing the CFD grid of the Cold-Top furnace
  • Establishing the future work-flow plans

The project partners are Celsian (lead investigator), RoMan Manufacturing, TECO and the Pacific Northwest National Laboratory (PNNL).

In addition, the team established base line recipes for the amber and flint tests. These recipes were chosen to represent real industrial glass melt formulas and be consistent across project members conducting tests in the CelSian lab, the PNNL lab, and through CFD modelling. Industrial-grade raw materials and post-consumer flint cullet were obtained from industrial steering committee partner Gallo Glass to maintain consistency with real-world industrial processes. Internal flint cullet was also obtained from a separate glass plant because of ease of acquisition.

For the quarter, five successful cold-top experiments were run on the Cold-Top furnace:

  • Container batch containing 30 percent post-consumer flint cullet at 2.0 tonnes/m2/day
  • Container batch containing 30 percent internal flint cullet at 2.0 tonnes/m2/day
  • Container batch containing 30 percent internal flint cullet at 1.75 tonnes/m2/day
  • Container batch containing 70 percent internal flint cullet at 2.0 tonnes/m2/day
  • 100 percent internal flint cullet at 2.0 tonnes/m2/day

Sign up for free to the glassOnline.com daily newsletter

Subscribe now to our daily newsletter for full coverage of everything you need to know about the world glass industry!

We don't send spam! Read our Privacy Policy for more information.

Share this article
Related news