A LiSEC stand-alone machine is an excellent choice for optimising production processes and increasing efficiency. However, there are some points to consider before starting installation, in order to ensure that everything goes smoothly and that the machine can be started up optimally.

Defining a central point of contact
Successful installation starts with designating a point of contact who has comprehensive information on the project. A central point of contact eases quick decision making and problem solving on-site, which minimises delays and ensures a smooth installation process.Ensuring deadline clarity
Another important aspect for successful cooperation is ensuring mutual understanding when it comes to the agreed deadlines. Both the delivery date and the start of installation must be clearly defined for all involved.Clarifying the air and power connections
An in-depth prior clarification of the connection values for air and power is another decisive factor for smooth installation. This clarification can take place in a meeting between the installation coordinators at LiSEC and the customer’s central point of contact around two weeks before the delivery date.Announcing the availability of lifting equipment
Advance information on the availability of the lifting equipment required for installation is decisive for managing delays and risks. It is important to clarify whether a crane, a forklift or no lifting equipment is available in advance. If a crane has to be organised, this can be planned in advance.Information regarding applicable safety requirements and legal regulations
Advance information on the local safety requirements or the safety topics relevant for the LiSEC fitters enables work to be planned and carried out efficiently. In this way, all people involved can ensure that they take the required precautions in order to prevent accidents and injuries, in accordance with the applicable laws.Prepared installation location
The last success factor is a well prepared location for installing the new machine. If the location for the machine is clean and clear for the LiSEC installation team, they can start work immediately. It is also very important to check the ground conditions with regard to unevenness and slopes.

Considering these six factors aids considerably with installing a LiSEC machine. LiSEC is available at any time to ensure that the process is as smooth as possible.





