Page 41 - Glass Machinery Plants & Accessories no. 6-2019
P. 41

MAIN PROJECTS IN 2019:
                                                                                 Bormioli Rocco, Altare plant,
                                                                               reconstruction of a furnace com-
                                                                               pleted at the end of March.
                                                                                 Bormioli Pharma, San Vito
                                                    Forehearth costruction
                                                                               plant: design and construction of a
                     Chambers Costruction                                      furnace, including structural work
                                                                               and installations. Reconstruction
                                                                               work from mid-May.
                                                                                 Bormioli Pharma, Bergantino
                                                                               plant: design and construction
                                                                               of a furnace, including struc-
                                                                               tural work and installations.
                                                                               Reconstruction work starting as
                                                                               of September.

                                                                               DESIGN
                                                                                 Tecsiglass design work starts
                                                                               right from the basic studies to
                                                                               create detailed projects, in con-
                                                                               stant contact with customers. The
                                                                               experience gained over the years
                                                    Superstructure Furnace     shows that good projects reduce
                                                                               risks and construction time.
            • furnace reconstruction;         for the following operations:      The company designs:
            • carpentry and metalwork;        • plating;                       • plant lay-outs;
            • plants;                         • spout changeover;              • refractory structures;
            • pre-heating.                    • sealing;                       • carpentry and metalwork;
                                              • refractory replacement.        • electrical-instrumental systems;
            HOT WORKING                                                        • specific systems and plants;
            AND MUCH MORE                     FURNACE RECONSTRUCTION           • software development;
               The company also takes part in   The work on each and every     • use and maintenance manuals. Q
            various R&D projects, in partner-  construction site is coordinated
            ship with experts and universi-   by a project manager, who super-
            ties. Moreover, Tecsiglass also has   vises and coordinates integration
            an emergency stock of refractory   between the various activities -
            materials available for its clients’   design, construction and assembly.
            needs, along with a hot-repair      Tecsiglass technical team and
            team available 365 days a year,   project manager, together with        TECSIGLASS
            both for emergency and sched-     its partner companies, ensure
            uled work, ready to carry out     that the project is carried out        Via Giovanni Nicotera 29
            work in the shortest time possible   flawlessly, in compliance with          00195 Roma - Italy
                                              timing requirements and safety         Tel.: +39-010-9913351
                                              regulations.                      E-mail: direzionegenerale@tecsiglass.com
                                                                                     www.tecsiglass.com
   36   37   38   39   40   41   42   43   44   45   46