Page 38 - Glass-Technology International no. 4/2017
P. 38

businessnews


           www.glassonline.com




           The renovation of the UNO build-                   SEDAK
           ing “United Nations Conference
           on Trade and Development” in                       LARGE GLASS FOR UNO
           Geneva shows how today’s pro-
           duction technology makes monumental protection possible   BUILDING IN GENEVA
           also for buildings with glass façades. The 13m-high insulat-
           ing glass units, which in 1971 had been fabricated manually   Also the colour had to fulfil specific requirements: For the
           and during an effortful process, had now to be replaced.   UNO building, it was only allowed to use standard float glass
           sedak delivered tempered double IGUs produced fully auto-  (green glass) which cannot be procured as fast as low-iron
           matically. The dimensions are still impressive.    glass. “We were able to offset the longer delivery time of
           It was a spectacular exchange: In 2016, parts of the glass   the raw material with the quick production at sedak,” says
           façade of the UNO building “United Nations Conference on   Scheurer. The insulating glass units had been manufactured
           Trade and Development” in Geneva (second headquarters   within just a few weeks.
           of the United Nations) were replaced. The about 45-year-  sedak produced a total of nine double IGUs out of 12mm
           old glazing had become foggy; some of the glass units had   thick basic glass (dimensions: three units in 2.29m x 7.84m,
           cracked; the bonding of the support structure of the glass fa-  six units in 2.29m x 13.10m). The single glass panes had
           çade had aged. Due to monumental protection, the new glass   been produced as heat-strengthened safety glass to guarantee
           units had to be true to the original, i.e. of the same oversize   a higher break resistance.
           dimensions. Additionally, the special supporting structure of   The metal blocks of the old façade were replaced by glass
           the building was supposed to be maintained.        blocks that were attached to the IGUs with a special adhe-
           The dimensions of the glass units were exceptional for   sive. “Before replacing the metal blocks, the contracted metal
           the year 1971. They were manufactured manually out of   engineering company had run special material test series in
           non-tempered glass and were said to be perhaps the largest   Lausanne. In the end, glass turned out to be the best material
           units that had been produced by then. Today, sedak provides   for the bonding. That shows once again how versatile glass
           tempered insulating glass up to 15m manufactured fully   is,” explains Scheurer.
           automatically.                                     sedak packed the insulating glass units in specially fabricated
           “To be able to install the glass in 1971, the building enve-  boxes which were adjusted to the dimensions of the formats
           lope was realized as a hanging façade. That principle had   and corresponded to the safety requirements with a support-
           to be kept in mind,“ says Ralf Scheurer, who was the sedak   ing structure.
           responsible for the project. It took the metal constructors   A low-bed trailer transported the glass units to Geneva where
           (Metallover SA, Carouge, Switzerland) about four months to   they were installed with a truck crane and a glass vacuum
           check whether the project is possible at all.      lifter. In September 2016, the installation was completed.




































           36 Glass-Technology International 4/2017
   33   34   35   36   37   38   39   40   41   42   43